Q3 Langley – Progress Report (May 2016)
Interserve Construction are currently completing week 31 of the 48 week build process. We are pleased to report that works to date are ahead of schedule and achieved water tightness in front of programme dates.
Internally, walls are progressing well, with classrooms fully built and painting commencing. Interserve will have a sample classroom complete in mid May 2016.